When will the Cross Island Line be opened?

53 views
The Cross Island Line (CRL) in Singapore is being constructed in several phases, each with its own completion timeline.
- Phase 1 (CRL1): This phase, which includes 12 stations from Aviation Park to Bright Hill, is expected to be completed and operational by 2030. It will serve areas such as Loyang, Tampines, Pasir Ris, Defu, Hougang, Serangoon North, and Ang Mo Kio.
- Phase 2 (CRL2): Construction for this phase, which comprises six underground stations from Turf City to Jurong Lake District, is set to commence in 2024 and is targeted to be completed by 2032.
- Punggol Extension: The Punggol Extension of the CRL, which will provide a direct link between eastern and north-eastern areas, has also commenced construction and is expected to be completed by 2032.
In summary, the Cross Island Line will be opened in stages, with the first phase ready by 2030 and subsequent phases by 2032.